Q: What is the construction schedule? What are the work hours for elevated noise levels?
A: The construction schedule is as follows:
Date | Work |
---|---|
DEC 2019 | Demolition & Debris Removal Start |
JUN 2020 | Shoring Construction Start |
DEC 2020 | Excavation Complete |
MAR 2021 | Podium Complete |
JAN 2022 | Topped Out |
DEC 2022 | Completion |
Notes:
- Construction schedule is subject to change without notice.
Day of Week | Hours |
---|---|
M-F: | 7:00 AM – 7:00 PM |
SAT: | 9:00 AM – 5:00 PM |
SUN: | None Expected |
Notes:
- Activities of extreme noise (>90 dBA) are only to be performed from 9:00 AM to 4:00 PM, M-F.
- Exceptions to working hours posted may apply, refer tot he City of Oakland for more details.